Construction Project
KHAIR CENTER
Our center is in the heart of the fast growing 422 corridor, minutes off of the Oaks exit. 3.5 acres of land and 140 parking spaces has been developed. Additional overflow of 100 parking spaces could be utilized.
Ready to move in
Fundraising Goal
READY TO GO
PAD-SITE
The lot is improved with a paved parking area (140 spaces, 8 handicapped), road improvements, fire hydrants, curb cuts, storm water retention and utilities.
timeline:
PHASE 1 – PURCHASE LOT – (completed 2/1/2018)
Purchase price: $1.35 million + closing costs + attorney fees/zoning needs = $1.5 million
Obtain appropriate zoning for Community Center use. (COMPLETED, 9/29/17)
Complete property purchase. (COMPLETED 2/1/18)
PHASE 2 – INTERIM SPACE (2017 – 2021) (COMPLETED)
Utilize partner organization IQRA Institute space for Jummah and other activities.
PHASE 2a – CONSTRUCT MASJID STRUCTURE (2021 – 2022) (COMPLETED 2023)
Construct the masjid portion of the building. Create custom fit-out of the mezzanine and directly below mezzanine as community and classroom space (temporary).
Become operational in new facility by Ramadan 2022. Migrate sister organization, IQRA Institute into new building.
Construct outdoor playground.
Develop with Architect construction documents to be approved for building permit
Raise funds for construction of Phase 2A.
Seek necessary approvals for master plan ongoing phases and timelines.
Continue to pay off Qard-ul-Hasana annual payments.
Build monthly Sustainer base.
PHASE 3 – CONSTRUCT COMMUNITY CENTER STRUCTURE (2025)
Build new exterior structure that will house a gym, classrooms, and activity space, youth center, office space, and more. (Community Center Portion).
Connect the masjid building and community center portion.
Raise funds for construction of Phase 3.
Build monthly Sustainer base.
PHASE (4-8) – INTERIOR FINISHING OF COMMUNITY CENETR (2025 – 2030)
Take a phased approach of finishing the interior portions of the community center of the building.
Included but not limited to: gym, classroom space, activity hall, office space, etc.
Raise funds for construction of each phase.
FINAL PHASE (2030)
Remove temporary classrooms and community rooms in masjid portion of the complex, and convert to dedicated masjid including carpeting, finishes, etc.